No. Project title Construction location Investor Year taken Construction level Group of project Work content Total investment

(million VND)

Contract value

(million VND)

1 Investing in improvement and upgrade of National Highway 6A pavement (Phung Khoang – Ba La section), Ha Dong District Hanoi City Ha Dong District People’s Committee 2014 Technical infrastructure work, grade III B Survey, preparation of working drawing design 273,315 1,165
2 Constructing technical infrastructure of cattle slaughterhouses in Binh Minh Commune, Thanh Oai District Hanoi City Thanh Oai District People’s Committee 2012 Technical infrastructure work, grade III B Survey, preparation of working drawing design 111,872 1,058
3 Constructing technical infrastructure of resettlement area for land recovery of some projects in Son Tay Town, Hanoi Hanoi City Son Tay Town People’s Committee 2016 Technical infrastructure work, grade III B Survey, preparation of working drawing design 58,931 237
4 Constructing technical infrastructure of the land use right auction area at ĐG 02 – Quoc Oai Town, Quoc Oai District, Hanoi City Quoc Oai District People’s Committee 2015 Technical infrastructure work, grade III B Survey, preparation of working drawing design 10 319
5 Technical infrastructure of Northern Phu Cat residential area, Thach That District, Hanoi City Thach That District People’s Committee 2007 Technical infrastructure work, grade III B Survey, preparation of working drawing design 400,000 5,281
6 Investing in renovation and upgrade of National Highway 6A pavement (Phung Khoang – Ba La section), Ha Dong District Hanoi City Ha Dong District People’s Committee 2014 Technical infrastructure work, grade III B Survey, preparation of working drawing design 273,315 4,086
7 Constructing technical infrastructure of service land areas LK29, LK30, LK31 (service land under planning 1/2000 of the northern urban area axis), Duong Noi Ward, Ha Dong District

 

Hanoi City Ha Dong District People’s Committee 2009 Technical infrastructure work, grade III B Survey, preparation of working drawing design 164,000 1,650
8 Constructing technical infrastructure of cattle slaughterhouses in Binh Minh Commune, Thanh Oai District Hanoi City Thanh Oai District People’s Committee 2012 Technical infrastructure work, grade III B Survey, preparation of working drawing design 111,872 1,058
9 Roads connecting the service land areas LK21, LK26, HT5 in La Khe Ward, Ha Dong District Hanoi City Ha Dong District Construction and Investment Project Management Unit 2011 Technical infrastructure work, grade III B Survey, preparation of working drawing design 70,000 880
10 Technical Infrastructure Area I – Dong Mai Service Land (Dong area, Nam Ninh, Ve A, Ve B) Hanoi City Ha Dong District People’s Committee 2008 Technical infrastructure work, grade III B Survey, preparation of working drawing Survey, preparation of working drawing design 100,000 451
11 Investing in the construction of resettlement area technical infrastructure in service of land clearance project of the Nouth-South main axis of Quoc Oai urban area Hanoi City Quoc Oai District People’s Committee 2012 Technical infrastructure work, grade III B Survey, preparation of working drawing design 36,400 358
12 Constructing technical infrastructure of the land use right auction area at ĐG 02 – Quoc Oai Town, Quoc Oai District, Hanoi City Quoc Oai District People’s Committee 2015 Technical infrastructure work, grade III B Survey, preparation of working drawing design 101 707